1. TOUCH SCREEN OPERATION
The touch screen operation is the same as First Wave system with more pages for second wave components. The icons are operated in the same way. It needs to be pointed out that RO autoclean time shall be adjusted as following: Pressing and holding the ...
2. SYSTEM STARTUP AND SHUTDOWN
WARNING: Ensure all isolation valves are fully open and that all vessel drains are fully closed prior to the startup of the system. Ensure that all the RO Clean in Place (CIP) Valves are fully closed. For Initial Startup of the Second Wave, Refer to ...
3. CHEMISTRY SETTING AND ADJUSTMENT
GOALS OF CHEMICAL TREATMENT Microscreen filtrate TSS Size of flocs on microscreen Strength of flocs on microscreen Bag filter dp alarm Goals <1.5% of Manure TSS Large Strong Less than once every 24 hours For more information on Microscreen chemistry ...
4. Clarifier
The operation of the Clarifier is dependent upon the amount of settled sludge in the cone of the Clarifier and the performance of the jar test samples taken before the inlet to the Clarifier. Before starting up the system, ensure the clarifier sludge ...
5. CARTRIDGE FILTER
CARTRIDGE FILTER CHANGE: If the differential pressure across the cartridge filters rises to 25 PSIG, the system will alarm and warn the operator that the filters should be replaced soon. If the differential pressure rises to 40 PSIG, the system will ...
6. REVERSE OSMOSIS (RO)
RO SET UP: The RO system is designed to recover 65-70% of the manure as clean water while concentrating the remaining dissolved solids as a nutrient fertilizer. The RO pressures are set by closing the concentrate valve halfway and allowing the system ...
7. MOTOR OPERATED VALVES
Motor Operated Valves (MOVs) are used in the system to form different flow paths for different system functions. The following table summarizes their function and corresponding control relays. The MOVs are equipped with a handle so that it can be ...
8. LAB ANALYSIS
The touch screen is programmed to continuously upload data to LWR's server every 5 minutes for analysis, provided the internet connection is working. This includes flow data and TSS values if grõCONTROL is included. The operator will also need to ...
9. Calibrating Chemical Feed Pumps
CALIBRATION OF CHEMICAL FEED PUMPS: The chemical feed pumps actual flow rates can differ from the calculated flow rate by as much as 2 times depending on the amount of back pressure provided by the process fluid. The pumps must be calibrated to ...
10. GRUNDFOS TRANSFER PUMP DESCALING
The transfer pump P-210 will have scale deposits build up on the impellors and bearings in the pump. This will lead to reduced pumping performance and eventually to the pump stalling. The scale is comprised of a mineral and iron scale. This scale is ...
11. GRUNDFOS AIR BLEED
The transfer pump P-210 and Clean-in-Place pump P-360 won’t function if there is any air trapped inside of the pump. The transfer pump will require bleeding any time the water has been drained out of it. Occasionally the Clean-in-Place pump will suck ...
12. MAINTENANCE AND OPERATIONAL CHECKS SUMMARY
The maintenance tasks are summarized as following: MAINTENANCE TASKS DAILY WEEKLY MONTHLY QUARTERLY ANNUALY Every 2 years Drain and clean the Clarifier (V-190) X Replace Cartridge Filter Cartridges X / As required RO Cleaning (AutoClean Process) X RO ...
13. GENERAL TROUBLESHOOTING
SYMPTOM CAUSE ACTION System won't start ESD Button Pushed Check that all ESD buttons are in their "OUT" position. Press 'RESET' Button Main Feeder Protection Tripped Check feeder protection for blown fuse or tripped circuit breaker. Check wiring for ...
14. ALARM CONDITIONS
ALARM CONDITIONS: The LWR Manure Treatment System is shut-down if any of the following safety limits are exceeded: Emergency Shutdown Button is pressed Pull ESD button out. LAHH-0901A, Inlet Tank (V-090A) High High Level – Optional Process manure in ...
15. LAB EQUIPMENT LIST
The lab equipment listed in the following are recommended for the operator to conduct necessary lab tests in order to fill out log sheets correctly. Hach DR900 Colorimeter (9385100) Pkg of 6 glass vials (2401906) TDS Tester (2520250) Conductivity ...
SW APPENDIX A: INITIAL SYSTEM STARTUP
WARNING: Ensure all isolation valves are fully open and that all vessel drains are fully closed prior to the startup of the system. Ensure that all the RO Clean in Place (CIP) Valves are fully closed. STARTUP SECOND WAVE STARTUP – CLARIFIER AND ...