10. Filtrate Tank Level Sensor and Switch Cleaning
FILTRATE TANK LEVEL SWITCH
CLEANING
To maintain the proper
functioning of the level sensors/switches in the holding tank after the
Microscreen, it is necessary to periodically clean them to remove any
accumulated solids.
LEVEL SENSOR/SWITCH CLEANING PROCEDURE
Follow the procedure below for cleaning the level
sensor/switch:
Ensure that both sections of the tank are empty before starting the cleaning
procedure.
Use a hose with a spray nozzle to wash down the level sensor tip
and switches. Note: Do
NOT use a power washer on the level sensor, as it may cause damage.
Direct the spray nozzle towards the level sensor tip and switches,
applying sufficient water pressure to remove any built-up material.
Continue washing until all the solids have been completely removed
from all the switches.
Once the cleaning is completed and the switches are free from
debris, ensure that the tank is refilled, and the system is ready for
operation.
Perform this level sensor/switch cleaning procedure
at least once a day to prevent any disruptions in their functionality.
By maintaining clean level sensors/switches, you can ensure accurate level
measurement and proper operation of the system.
Related Articles
6. Floc Tank Setup, Optimization and Operation
FLOCCULATION TANK The flocculation tank plays a crucial role in the treatment process by mixing the injected polymer with the manure before it flows over the Microscreen unit. To ensure effective floc formation while minimizing the use of chemicals, ...
11. Maintenance Summary
MAINTENANCE TASKS DAILY WEEKLY MONTHLY ANNUALY Every 2 years Drain and clean filtrate tank V-170 X Inspect to make sure all polymer distribution lines are clear and free flowing X Inspect screen for tares or damages X Drain and clean screw press ...
14. ALARM CONDITIONS
ALARM CONDITIONS: The LWR Manure Treatment System is shut-down if any of the following safety limits are exceeded: Emergency Shutdown Button is pressed Pull ESD button out. LAHH-0901A, Inlet Tank (V-090A) High High Level – Optional Process manure in ...
4. Microscreen Setup and Operation
MICROSCREEN Microscreen Setup Proper setup of the Microscreen involves adjusting two devices to ensure effective draining of solids through the screen surface. These devices are the floc tank adjustment and the screen angle adjustment. FLOC TANK ...
5. Screw Press Setup and Operation
SCREW PRESS When operating the screw press, adjustments may be necessary to achieve the desired moisture content in the solids. The moisture content can be controlled by adjusting the pressure at the outlet of the screw press. Here are some ...